For a straight interior wall, order 5–7% above your net area. A façade chopped up by windows needs 8–12%. Curved columns run 15–20%. If that is all you came for, take the number and go measure.
The rest of this page is the arithmetic behind those figures. Take-offs that land short are rarely short on the wall face. They come up short on returns, reveals, offcut reuse, and whatever has to sit in a store room for two years until a trolley clips a corner.
Four numbers explain nearly all of it.
Applies to flexible stone veneer — the 2–9 mm modified clay panels also sold as MCM, soft stone or flexible stone cladding — in 600 × 1200 mm and 1200 × 2400 mm formats, at 3.0–10.5 kg/m². How the panels go up is covered in the installation guide. This page only deals with the number that goes on the purchase order.
Start with net area, and be honest about it
Net area is the flat face you are covering, measured twice, in metres. Length times height, per elevation, summed.
That is the easy part.
Measure twice. Nobody has ever produced a usable take-off from a photograph and a room schedule.
Three decisions change that number before any waste allowance gets applied.
Openings. Deduct windows, doors and pass-throughs over roughly 1 m². Leave small penetrations alone — a 300 mm socket box does not save you a panel, and deducting twenty of them is how a take-off ends up 4 m² light.
Returns and reveals. This is where most orders go wrong. A 200 mm return at each window jamb on a building with sixty windows works out at more than 20 m² of material that appears on no drawing and in no area schedule. Reveals around a recessed entrance add more again. Measure them as separate rectangles and add them, rather than assuming the wall face already covers it.
Both faces. A partition clad on two sides is two areas. It sounds obvious until someone quotes a single-sided figure for a freestanding wall in the middle of a hotel lobby.
| Element | Include in net area? | Typical addition on a punched façade |
|---|---|---|
| Main wall face | Yes, always | — |
| Window and door openings | Deduct if over 1 m² | −12 to −25% |
| Jambs, reveals, returns | Yes, add separately | +5 to +9% |
| Soffits and ceiling margins | Yes | +2 to +5% |
| Column boxing and pilasters | Yes, all four faces | +3 to +8% |
| Skirting rebates and shadow gaps | No | — |
Add the returns and soffits to the wall face first. Only then apply a waste allowance. Doing it the other way round — waste on the wall face, returns remembered later — is the single most common reason a container arrives one pallet short.
Waste allowances that hold up on site
Waste is not a punishment. It is the insurance you pay against running out three panels from the top of a four-storey lift shaft, with no way of matching the batch, no way of finishing the elevation, and a client walk-through booked for the Friday morning.
| Layout | Allowance | What drives it |
|---|---|---|
| Straight lay, few openings, large flat walls | 5–7% | Edge trim, end-of-run cuts |
| Many openings, column boxing, short runs | 8–12% | Offcuts too small to reuse on the next run |
| Diagonal, chevron or herringbone | 12–18% | Every cut is an angled cut, both ends waste |
| Curved walls and round columns | 15–20% | Template cutting, test fitting, kerf loss |
| Pattern-matched or vein-matched textures | 12–15% | Panels can only be placed one way up |
| Repair stock, held separately | 3–5% | Not waste. See below. |
Two of these deserve a note, and both have caught out people who have been writing take-offs for twenty years.
Diagonal work is expensive in material. Nobody warns the client. A 45° lay on a 2.4 m high wall produces a triangular offcut at every course change, and half are the wrong way round for the next course. Take the top of the range.
Pattern matching matters more with MCM than with tile, because the texture is a printed and pressed face rather than a glazed surface. Two panels of the same colour from a vein-matched texture are not interchangeable. If the design calls for book-matched piers, order the matched set as its own line item with its own allowance.
Panel format decides where the offcuts land
Two formats are standard: 600 × 1200 mm, which is 0.72 m² per panel, and 1200 × 2400 mm at 2.88 m². Format does not change the wall area. It changes how much of each panel survives the cut, and that is the entire trade-off between the two sizes.
Large format wins on tall, uninterrupted walls. A 2.8 m ceiling with 2400 mm panels leaves a 400 mm band, and that band is exactly the width you want for a shadow gap or a skirting detail, so nothing is wasted. The same 2400 mm panel on a 2.4 m high corridor with a door every 4 m produces a 1.2 m offcut at each opening, and those offcuts only fit if the next run starts off the same datum.
Small format wins on curves, columns, and fiddly geometry. A 600 × 1200 panel bends to a tighter radius before the face starts to craze, and a ruined 0.72 m² panel hurts a good deal less than a ruined 2.88 m² one.
Practical rule for a project with both: large format on flat runs, small format on curved and broken work. Never split a mixed-format order by guesswork when the drawing will tell you which wall is which.
Split by format.
A worked example: 240 m² of hotel corridor
Corridor cladding, one face, 96 m long, 2.5 m high. Fourteen door openings at 2.1 m high and 1.0 m wide. Two lift lobbies with column boxing. One texture, one colour, 1200 × 2400 mm.
Start with 96 × 2.5 = 240 m² gross.
Deduct the openings: 14 × 2.1 × 1.0 = 29.4 m². That leaves 210.6 m² of flat face.
So far, so ordinary.
Now the parts that get forgotten. Door reveals at 200 mm deep, two sides and a head per opening, come to roughly 15.4 m². Column boxing on two lobbies adds around 9 m². Shadow gaps and the top band under a 2.7 m soffit add 6 m².
Net area: 210.6 + 15.4 + 9 + 6 = 241 m².
Notice what happened. Gross 240. Net 241.
Two large deductions were cancelled by three small additions, and anyone who quoted the gross figure plus 5% landed at 252 — close, but for the wrong reasons, and one door detail away from running short on the top floor.
Apply the allowance. Fourteen openings, no diagonal work, decent run lengths: 8%.
241 × 1.08 = 260.3 m².
Add repair stock at 4% of net: 9.6 m². Keep it as a separate line on the order and a separate pallet in the store, because the moment it joins general stock it becomes installation material and quietly disappears.
Order quantity: 270 m². Split 260 to site, 10 held back.
Then check it against the commercial terms. Minimum order quantities apply per texture and per colour, so a single texture and colour means one minimum, not three. Change the corridor to two textures and you have just bought two minimums, which is a far more reliable way to lose a project margin than any waste factor. Ordering terms sit in the B2B procurement terms.
Why the number is usually smaller than the tile equivalent
Tile waste runs 10–15% on a straightforward job, higher in small rooms. MCM rarely needs that much. Three reasons.
Cutting is done with a utility knife or a pair of shears, straight through the sheet. No wet saw, no chipped edges, no water on the face. One cut, one line, no kerf to allow for.
The sheet is flexible. It bends at a corner instead of snapping, which cuts breakage during handling and stacking — usually the largest hidden loss on a tile job and one that installers habitually underestimate because it never appears on a delivery note.
Offcuts stay usable down to roughly 100 mm strips, because the material is thin enough to trim square again. Keep them. You will want them at the reveals. A tile offcut under 150 mm is bin material. A veneer strip at 100 mm is a reveal liner.
The counterweight is weight, which sounds contradictory until the freight maths lands. At 6 mm the material runs about 6 kg/m², so that 270 m² corridor order arrives at close to 1.6 tonnes, on pallets, flat. It does not want to be stored upright against a wall for a fortnight. Handling is part of the order.
What to hold back, and how to store it
Repair stock of 3–5% of net area. Not waste, not spare, and not a buffer against a bad take-off. A separate line, kept for the day someone drills through a wall and finds a pipe that was not on the drawing.
Three rules for it. All of them cheap.
Same production batch as the main order. Colour matching across batches is the one thing nobody can fix afterwards. Put the repair stock on the same purchase order, and ask for it to be packed from the same run.
Store flat, indoors, on the pallet it arrived on. Upright storage bows the sheets, and a bowed sheet will not sit tight to a wall however much adhesive goes behind it. Damp store rooms and direct sun both leave marks that do not wash off.
Label it. Texture name, colour code, thickness, and the elevation it belongs to. Six months later, in a container yard, nobody remembers which of four pallets was the corridor.
Five places the maths quietly falls apart
Mixed thickness on one elevation. A 2 mm and a 6 mm panel are not interchangeable, even in the same colour. Change thickness halfway up a façade and you have two orders with two allowances. Thickness selection has its own logic, covered in the thickness selection guide.
Late design changes. Any revision after the order is placed risks a different batch. Budget the revision as a separate quantity rather than hoping the 8% covers it.
Soffits measured last. They are always measured last, they are always the smallest figure on the sheet, and they are always the reason the final elevation runs short while everyone stands around blaming the supplier.
Curves templated on site. Round columns get measured, template-cut and test-fitted. Allow at least one full panel per column as a test piece, and do not assume the test piece can be installed.
Cladding that becomes a feature wall. Once a client sees the material up, the plain wall three metres away tends to become a feature wall too. Leave the option in the quantity conversation, not in an emergency re-order.
Frequently Asked Questions
Do I deduct windows and doors from the wall area?
Deduct openings larger than about 1 m², then add the jamb and reveal depth back as a separate area. A 1.0 × 2.1 m door removes 2.1 m² of face but returns roughly 0.6 m² of reveal, so the net saving is smaller than it looks. Leave small penetrations in the measured area.
How much extra should I order for a curved wall?
Allow 15–20% over the developed area. Curved work is templated, test-fitted and kerfed, and a round column often consumes two panels before a single acceptable one reaches the wall. Order high once rather than low twice.
Can offcuts from one floor be used on another?
Only from the same batch, and only for the same texture and colour. Physically the material will fit anywhere. Visually, a panel cut from a different run may read slightly warmer or cooler under raking light, which is exactly the condition corridors and lobbies are lit for.
How much repair stock should I keep?
3–5% of net area, from the same production batch, stored flat and labelled. Buildings get drilled, trolleys hit corners, signage gets moved. The stock adds a few percent to the order and saves replacing a whole elevation later.
Does thickness change how much material I need?
No. Area is area. Thickness changes weight, stiffness, and how the panel behaves at a curve or an external corner — not the square metre count. It does change the weight per square metre, from 3.0 kg/m² at the thin end to 10.5 kg/m² at the thick end, and that matters for pallet planning and lift capacity.
Send the drawings, not the square metres
A single area figure is a guess dressed as a quantity. Elevations with a scale, a door schedule and a note on which walls are curved will produce a take-off that survives contact with a site.
We work through quantities from drawings on most enquiries, and the answers usually move the number further than the waste factor does. Face options are in the texture catalogue, technical data is in the specifications sheet, packing and shipping volumes are in the logistics guide, and fixing and cutting are covered by the adhesive guide and the cutting guide.